Storage power plant · Pecos, TX
Hydra
Hydra is a 200 MW storage power plant in Pecos County, Texas, operated by Engie North America. Its oldest generator still running came online in 2024.
Hydra in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 19th largest, about 1.2% of the state's 16 GW of storage capacity.
Pecos County has 31 power plants of 1 MW or more with 3.7 GW in all; Hydra is 5% of that and the largest of 12 storage plants there.
The average electricity customer in Pecos County goes 8.6 hours a year without power, the 132nd most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Hydra (outlined) and other plants in Pecos County, shaded. 30.993, -102.290.
Plant facts
- Operator
- Engie North America
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Pecos County, TX
- EIA plant ID
- 65490
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| HYDRA | Batteries | 200 MW · 200 MWh | 2024 | – |
Questions
Hydra, answered
How much can Hydra store and deliver?
Hydra can deliver up to 200 MW and hold 200 MWh of energy, from one battery or storage system. Its net energy in 2025 was -22.0 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Hydra?
Hydra is in Pecos County, Texas, at about 30.993°, -102.290°. It is one of 31 power plants of 1 MW or more in the county. The average electricity customer in Pecos County goes 8.6 hours a year without power, the 132nd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Hydra?
It is operated by Engie North America (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Hydra open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Methodology.