Wind power plant · Barnes, ND

FPL Energy Ashtabula Wind LLC

FPL Energy Ashtabula Wind LLC is a 149 MW wind power plant in Barnes County, North Dakota, operated by FPL Energy Ashtabula Wind LLC. Its oldest generator still running came online in 2008. In 2025 it generated 583 GWh, about what 45,000 average North Dakota homes use in a year.

Capacity149 MWNameplate, September 2026
Generated583 GWhIn 2025
Capacity factor45%Share of the most it could make, 2025
Generators1Oldest from 2008

FPL Energy Ashtabula Wind LLC in context

Among the 42 wind plants in North Dakota in the EIA's inventory, it is the 18th largest, about 3.0% of the state's 5.0 GW of wind capacity.

Barnes County has 3 power plants of 1 MW or more with 259 MW in all; FPL Energy Ashtabula Wind LLC is 57% of that and the largest of 3 wind plants there.

Its capacity factor of 45% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Barnes County goes 6.9 hours a year without power, the 7th most of 13 counties in North Dakota. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060080020182019202020212022202320242025GWh 583
02004006008002019202120232025583

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

FPL Energy Ashtabula Wind LLC (outlined) and other plants in Barnes County, shaded. 47.129, -97.885.

Plant facts

Operator
FPL Energy Ashtabula Wind LLC
Sector
IPP Non-CHP
Grid operator
MISO
County
Barnes County, ND
EIA plant ID
56919
Where North Dakota's power comes from → North Dakota power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GE15 Onshore Wind Turbine 149 MW 2008 –

Questions

FPL Energy Ashtabula Wind LLC, answered

How much power does FPL Energy Ashtabula Wind LLC produce?

FPL Energy Ashtabula Wind LLC has 149 MW of capacity from one generator. In 2025 it generated 583 GWh, 45% of the most it could have made running flat out all year (its capacity factor).

How many homes does FPL Energy Ashtabula Wind LLC power?

Its 2025 output of 583 GWh equals the yearly electricity use of about 45,000 average North Dakota homes (1,070 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is FPL Energy Ashtabula Wind LLC?

FPL Energy Ashtabula Wind LLC is in Barnes County, North Dakota, at about 47.129°, -97.885°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Barnes County goes 6.9 hours a year without power, the 7th most of 13 counties in North Dakota. The county's page has the full outage record.

Who operates FPL Energy Ashtabula Wind LLC?

It is operated by FPL Energy Ashtabula Wind LLC (EIA sector: IPP Non-CHP), and it feeds MISO.

When did FPL Energy Ashtabula Wind LLC open?

Its oldest generator still running came online in 2008.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average North Dakota home's 1,070 kWh a month in 2025. Methodology.