Solar power plant · Fresno, CA
Fresno Community Solar
Fresno Community Solar is a 10 MW solar power plant in Fresno County, California, operated by Agilitas Energy, Inc.. Its oldest generator still running came online in 2024. In 2025 it generated 17 GWh, about what 2,900 average California homes use in a year.
Fresno Community Solar in context
Among the 967 solar plants in California in the EIA's inventory, it is the 295th largest, about 0.0% of the state's 32 GW of solar capacity.
Fresno County has 105 power plants of 1 MW or more with 5.9 GW in all; Fresno Community Solar is 0% of that and the 29th largest of 73 solar plants there.
Its capacity factor of 19% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Fresno Community Solar (outlined) and other plants in Fresno County, shaded. 36.696, -119.885.
Plant facts
- Operator
- Agilitas Energy, Inc.
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Fresno County, CA
- EIA plant ID
- 66715
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| FREPV | Solar Photovoltaic | 10 MW | 2024 | – |
Questions
Fresno Community Solar, answered
How much power does Fresno Community Solar produce?
Fresno Community Solar has 10 MW of capacity from one generator. In 2025 it generated 17 GWh, 19% of the most it could have made running flat out all year (its capacity factor).
How many homes does Fresno Community Solar power?
Its 2025 output of 17 GWh equals the yearly electricity use of about 2,900 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Fresno Community Solar?
Fresno Community Solar is in Fresno County, California, at about 36.696°, -119.885°. It is one of 105 power plants of 1 MW or more in the county. The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.
Who operates Fresno Community Solar?
It is operated by Agilitas Energy, Inc. (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Fresno Community Solar open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.