Solar power plant · Fresno, CA
Gates Solar Station
Gates Solar Station is a 20 MW solar power plant in Fresno County, California, operated by Pacific Gas & Electric Co.. Its oldest generator still running came online in 2013. In 2025 it generated 31 GWh, about what 5,100 average California homes use in a year.
Gates Solar Station in context
Among the 967 solar plants in California in the EIA's inventory, it is the 173rd largest, about 0.1% of the state's 32 GW of solar capacity.
Fresno County has 105 power plants of 1 MW or more with 5.9 GW in all; Gates Solar Station is 0% of that and the 16th largest of 73 solar plants there.
Its capacity factor of 17% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Gates Solar Station (outlined) and other plants in Fresno County, shaded. 36.176, -120.114.
Plant facts
- Operator
- Pacific Gas & Electric Co.
- Sector
- Electric Utility
- Grid operator
- CISO
- County
- Fresno County, CA
- EIA plant ID
- 57892
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 20 MW | 2013 | – |
Questions
Gates Solar Station, answered
How much power does Gates Solar Station produce?
Gates Solar Station has 20 MW of capacity from one generator. In 2025 it generated 31 GWh, 17% of the most it could have made running flat out all year (its capacity factor).
How many homes does Gates Solar Station power?
Its 2025 output of 31 GWh equals the yearly electricity use of about 5,100 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Gates Solar Station?
Gates Solar Station is in Fresno County, California, at about 36.176°, -120.114°. It is one of 105 power plants of 1 MW or more in the county. The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.
Who operates Gates Solar Station?
It is operated by Pacific Gas & Electric Co. (EIA sector: Electric Utility), and it feeds the California ISO.
When did Gates Solar Station open?
Its oldest generator still running came online in 2013.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.