Solar power plant · Jack, TX
Hecate Energy Longhorn Solar LLC
Hecate Energy Longhorn Solar LLC is a 650 MW solar power plant in Jack County, Texas, operated by Repsol Renewables NA. Its oldest generator still running came online in 2026.
Hecate Energy Longhorn Solar LLC in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the largest, about 1.7% of the state's 37 GW of solar capacity.
Jack County has 4 power plants of 1 MW or more with 1.0 GW in all; Hecate Energy Longhorn Solar LLC is 63% of that.
The average electricity customer in Jack County goes 11 hours a year without power, the 105th most of 240 counties in Texas. The county's page has the full outage record.
Where it is
Hecate Energy Longhorn Solar LLC (outlined) and other plants in Jack County, shaded. 33.044, -98.341.
Plant facts
- Operator
- Repsol Renewables NA
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Jack County, TX
- EIA plant ID
- 68839
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| RRPS | Solar Photovoltaic | 650 MW | 2026 | – |
Nearby
Other plants in Jack County
Questions
Hecate Energy Longhorn Solar LLC, answered
How much power does Hecate Energy Longhorn Solar LLC produce?
Hecate Energy Longhorn Solar LLC has 650 MW of capacity from one generator. No full year of generation is reported yet.
Where is Hecate Energy Longhorn Solar LLC?
Hecate Energy Longhorn Solar LLC is in Jack County, Texas, at about 33.044°, -98.341°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Jack County goes 11 hours a year without power, the 105th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Hecate Energy Longhorn Solar LLC?
It is operated by Repsol Renewables NA (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Hecate Energy Longhorn Solar LLC open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.