Solar power plant · Emery, UT
Hunter Solar LLC (UT)
Hunter Solar LLC (UT) is a 100 MW solar power plant in Emery County, Utah, operated by Hunter Solar LLC. Its oldest generator still running came online in 2021. In 2025 it generated 260 GWh, about what 28,000 average Utah homes use in a year.
Hunter Solar LLC (UT) in context
Among the 56 solar plants in Utah in the EIA's inventory, it is the 5th largest, about 3.3% of the state's 3.0 GW of solar capacity.
Emery County has 7 power plants of 1 MW or more with 3.7 GW in all; Hunter Solar LLC (UT) is 3% of that and the 2nd largest of 4 solar plants there.
Its capacity factor of 30% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Emery County goes 3.1 hours a year without power, the 13th most of 23 counties in Utah. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Hunter Solar LLC (UT) (outlined) and other plants in Emery County, shaded. 39.142, -111.051.
Plant facts
- Operator
- Hunter Solar LLC
- Sector
- IPP Non-CHP
- Grid operator
- PACE
- County
- Emery County, UT
- EIA plant ID
- 62656
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| HUSOL | Solar Photovoltaic | 100 MW | 2021 | – |
Questions
Hunter Solar LLC (UT), answered
How much power does Hunter Solar LLC (UT) produce?
Hunter Solar LLC (UT) has 100 MW of capacity from one generator. In 2025 it generated 260 GWh, 30% of the most it could have made running flat out all year (its capacity factor).
How many homes does Hunter Solar LLC (UT) power?
Its 2025 output of 260 GWh equals the yearly electricity use of about 28,000 average Utah homes (761 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Hunter Solar LLC (UT)?
Hunter Solar LLC (UT) is in Emery County, Utah, at about 39.142°, -111.051°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Emery County goes 3.1 hours a year without power, the 13th most of 23 counties in Utah. The county's page has the full outage record.
Who operates Hunter Solar LLC (UT)?
It is operated by Hunter Solar LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.
When did Hunter Solar LLC (UT) open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Utah home's 761 kWh a month in 2025. Methodology.