Storage power plant · Fresno, CA
J S Eastwood
J S Eastwood is a 200 MW storage power plant in Fresno County, California, operated by Southern California Edison Co. Its oldest generator still running came online in 1987. In 2025 it generated 87 GWh, about what 15,000 average California homes use in a year.
J S Eastwood in context
Among the 156 storage plants in California in the EIA's inventory, it is the 19th largest, about 1.5% of the state's 13 GW of storage capacity.
Fresno County has 105 power plants of 1 MW or more with 5.9 GW in all; J S Eastwood is 3% of that and the 2nd largest of 3 storage plants there.
The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
J S Eastwood (outlined) and other plants in Fresno County, shaded. 37.148, -119.257.
Plant facts
- Operator
- Southern California Edison Co
- Sector
- Electric Utility
- Grid operator
- CISO
- County
- Fresno County, CA
- EIA plant ID
- 104
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Hydroelectric Pumped Storage | 200 MW | 1987 | – |
Questions
J S Eastwood, answered
How much can J S Eastwood store and deliver?
J S Eastwood can deliver up to 200 MW, from one battery or storage system. Its net energy in 2025 was 87 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is J S Eastwood?
J S Eastwood is in Fresno County, California, at about 37.148°, -119.257°. It is one of 105 power plants of 1 MW or more in the county. The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.
Who operates J S Eastwood?
It is operated by Southern California Edison Co (EIA sector: Electric Utility), and it feeds the California ISO.
When did J S Eastwood open?
Its oldest generator still running came online in 1987.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.