Solar power plant · Upton, TX
King Mountain Solar
King Mountain Solar is a 175 MW solar power plant in Upton County, Texas, operated by King Mountain Solar, LLC. Its oldest generator still running came online in 2026.
King Mountain Solar in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 102nd largest, about 0.5% of the state's 37 GW of solar capacity.
Upton County has 8 power plants of 1 MW or more with 2.0 GW in all; King Mountain Solar is 9% of that and the 3rd largest of 4 solar plants there.
The average electricity customer in Upton County goes 15 hours a year without power, the 73rd most of 240 counties in Texas. The county's page has the full outage record.
Where it is
King Mountain Solar (outlined) and other plants in Upton County, shaded. 31.236, -102.123.
Plant facts
- Operator
- King Mountain Solar, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Upton County, TX
- EIA plant ID
- 69755
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 5568 | Solar Photovoltaic | 175 MW | 2026 | – |
Questions
King Mountain Solar, answered
How much power does King Mountain Solar produce?
King Mountain Solar has 175 MW of capacity from one generator. No full year of generation is reported yet.
Where is King Mountain Solar?
King Mountain Solar is in Upton County, Texas, at about 31.236°, -102.123°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Upton County goes 15 hours a year without power, the 73rd most of 240 counties in Texas. The county's page has the full outage record.
Who operates King Mountain Solar?
It is operated by King Mountain Solar, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did King Mountain Solar open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.