Storage power plant · Upton, TX
Upton County BESS
Upton County BESS is a 25 MW storage power plant in Upton County, Texas, operated by VESI Upton County BESS, LLC. Its oldest generator still running came online in 2023.
Upton County BESS in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 103rd largest, about 0.2% of the state's 16 GW of storage capacity.
Upton County has 8 power plants of 1 MW or more with 2.0 GW in all; Upton County BESS is 1% of that.
The average electricity customer in Upton County goes 15 hours a year without power, the 73rd most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Upton County BESS (outlined) and other plants in Upton County, shaded. 31.239, -102.322.
Plant facts
- Operator
- VESI Upton County BESS, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Upton County, TX
- EIA plant ID
- 64811
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| UPT1 | Batteries | 25 MW · 25 MWh | 2023 | – |
Questions
Upton County BESS, answered
How much can Upton County BESS store and deliver?
Upton County BESS can deliver up to 25 MW and hold 25 MWh of energy, from one battery or storage system. Its net energy in 2025 was -1.3 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Upton County BESS?
Upton County BESS is in Upton County, Texas, at about 31.239°, -102.322°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Upton County goes 15 hours a year without power, the 73rd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Upton County BESS?
It is operated by VESI Upton County BESS, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Upton County BESS open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Methodology.