Wind power plant · Klickitat, WA

Linden Wind Energy Project

Linden Wind Energy Project is a 50 MW wind power plant in Klickitat County, Washington, operated by Los Angeles Department of Water & Power. Its oldest generator still running came online in 2010. In 2025 it generated 104 GWh, about what 9,200 average Washington homes use in a year.

Capacity50 MWNameplate, September 2026
Generated104 GWhIn 2025
Capacity factor24%Share of the most it could make, 2025
Generators1Oldest from 2010

Linden Wind Energy Project in context

Among the 23 wind plants in Washington in the EIA's inventory, it is the 21st largest, about 1.5% of the state's 3.4 GW of wind capacity.

Klickitat County has 11 power plants of 1 MW or more with 1.7 GW in all; Linden Wind Energy Project is 3% of that and the 9th largest of 9 wind plants there.

Its capacity factor of 24% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Klickitat County goes 0.6 hours a year without power. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020020182019202020212022202320242025GWh 104
0501001502002019202120232025104

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Linden Wind Energy Project (outlined) and other plants in Klickitat County, shaded. 45.744, -120.784.

Plant facts

Operator
Los Angeles Department of Water & Power
Sector
Electric Utility
Grid operator
BPAT
County
Klickitat County, WA
EIA plant ID
57635
Where Washington's power comes from → Washington power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
LW1 Onshore Wind Turbine 50 MW 2010 –

Questions

Linden Wind Energy Project, answered

How much power does Linden Wind Energy Project produce?

Linden Wind Energy Project has 50 MW of capacity from one generator. In 2025 it generated 104 GWh, 24% of the most it could have made running flat out all year (its capacity factor).

How many homes does Linden Wind Energy Project power?

Its 2025 output of 104 GWh equals the yearly electricity use of about 9,200 average Washington homes (945 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Linden Wind Energy Project?

Linden Wind Energy Project is in Klickitat County, Washington, at about 45.744°, -120.784°. It is one of 11 power plants of 1 MW or more in the county. The average electricity customer in Klickitat County goes 0.6 hours a year without power. The county's page has the full outage record.

Who operates Linden Wind Energy Project?

It is operated by Los Angeles Department of Water & Power (EIA sector: Electric Utility), and it feeds the Bonneville Power Administration.

When did Linden Wind Energy Project open?

Its oldest generator still running came online in 2010.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Washington home's 945 kWh a month in 2025. Methodology.