Wind power plant · Carson, TX

Majestic II Wind

Majestic II Wind is a 80 MW wind power plant in Carson County, Texas, operated by NextEra Energy Majestic Wind. Its oldest generator still running came online in 2012. In 2025 it generated 180 GWh, about what 13,000 average Texas homes use in a year.

Capacity80 MWNameplate, September 2026
Generated180 GWhIn 2025
Capacity factor26%Share of the most it could make, 2025
Generators1Oldest from 2012

Majestic II Wind in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 202nd largest, about 0.2% of the state's 45 GW of wind capacity.

Carson County has 9 power plants of 1 MW or more with 1.2 GW in all; Majestic II Wind is 7% of that and the 7th largest of 9 wind plants there.

Its capacity factor of 26% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Carson County goes 14 hours a year without power, the 84th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 180
01002003004002019202120232025180

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Majestic II Wind (outlined) and other plants in Carson County, shaded. 35.386, -101.579.

Plant facts

Operator
NextEra Energy Majestic Wind
Sector
IPP Non-CHP
Grid operator
SWPP
County
Carson County, TX
EIA plant ID
58363
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
WND1 Onshore Wind Turbine 80 MW 2012 –

Questions

Majestic II Wind, answered

How much power does Majestic II Wind produce?

Majestic II Wind has 80 MW of capacity from one generator. In 2025 it generated 180 GWh, 26% of the most it could have made running flat out all year (its capacity factor).

How many homes does Majestic II Wind power?

Its 2025 output of 180 GWh equals the yearly electricity use of about 13,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Majestic II Wind?

Majestic II Wind is in Carson County, Texas, at about 35.386°, -101.579°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Carson County goes 14 hours a year without power, the 84th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Majestic II Wind?

It is operated by NextEra Energy Majestic Wind (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Majestic II Wind open?

Its oldest generator still running came online in 2012.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.