Natural gas power plant · Alameda, CA
Mariposa Energy Project
Mariposa Energy Project is a 200 MW natural gas power plant in Alameda County, California, operated by Diamond Generating Corporation. Its oldest generator still running came online in 2012. In 2025 it generated 29 GWh, about what 4,900 average California homes use in a year.
Mariposa Energy Project in context
Among the 304 natural gas plants in California in the EIA's inventory, it is the 51st largest, about 0.5% of the state's 41 GW of natural gas capacity.
Alameda County has 33 power plants of 1 MW or more with 1.6 GW in all; Mariposa Energy Project is 13% of that and the 2nd largest of 11 natural gas plants there.
Its capacity factor of 2% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Alameda County goes 3.6 hours a year without power, the 47th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Mariposa Energy Project (outlined) and other plants in Alameda County, shaded. 37.789, -121.602.
Plant facts
- Operator
- Diamond Generating Corporation
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Alameda County, CA
- EIA plant ID
- 57483
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CTG1 | Natural Gas Fired Combustion Turbine | 50 MW | 2012 | – |
| CTG2 | Natural Gas Fired Combustion Turbine | 50 MW | 2012 | – |
| CTG3 | Natural Gas Fired Combustion Turbine | 50 MW | 2012 | – |
| CTG4 | Natural Gas Fired Combustion Turbine | 50 MW | 2012 | – |
Questions
Mariposa Energy Project, answered
How much power does Mariposa Energy Project produce?
Mariposa Energy Project has 200 MW of capacity from 4 generators. In 2025 it generated 29 GWh, 2% of the most it could have made running flat out all year (its capacity factor).
How many homes does Mariposa Energy Project power?
Its 2025 output of 29 GWh equals the yearly electricity use of about 4,900 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Mariposa Energy Project?
Mariposa Energy Project is in Alameda County, California, at about 37.789°, -121.602°. It is one of 33 power plants of 1 MW or more in the county. The average electricity customer in Alameda County goes 3.6 hours a year without power, the 47th most of 56 counties in California. The county's page has the full outage record.
Who operates Mariposa Energy Project?
It is operated by Diamond Generating Corporation (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Mariposa Energy Project open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.