Wind power plant · Grady, OK

Minco Wind I, LLC

Minco Wind I, LLC is a 99 MW wind power plant in Grady County, Oklahoma, operated by FPLE Wind, LLC. Its oldest generator still running came online in 2010. In 2025 it generated 326 GWh, about what 25,000 average Oklahoma homes use in a year.

Capacity99 MWNameplate, September 2026
Generated326 GWhIn 2025
Capacity factor38%Share of the most it could make, 2025
Generators1Oldest from 2010

Minco Wind I, LLC in context

Among the 70 wind plants in Oklahoma in the EIA's inventory, it is the 61st largest, about 0.7% of the state's 13 GW of wind capacity.

Grady County has 7 power plants of 1 MW or more with 486 MW in all; Minco Wind I, LLC is 20% of that and the 3rd largest of 4 wind plants there.

Its capacity factor of 38% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Grady County goes 9.4 hours a year without power, the 17th most of 75 counties in Oklahoma. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 326
01002003004002019202120232025326

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Minco Wind I, LLC (outlined) and other plants in Grady County, shaded. 35.280, -97.976.

Plant facts

Operator
FPLE Wind, LLC
Sector
IPP Non-CHP
Grid operator
SWPP
County
Grady County, OK
EIA plant ID
57590
Where Oklahoma's power comes from → Oklahoma power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 99 MW 2010 –

Questions

Minco Wind I, LLC, answered

How much power does Minco Wind I, LLC produce?

Minco Wind I, LLC has 99 MW of capacity from one generator. In 2025 it generated 326 GWh, 38% of the most it could have made running flat out all year (its capacity factor).

How many homes does Minco Wind I, LLC power?

Its 2025 output of 326 GWh equals the yearly electricity use of about 25,000 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Minco Wind I, LLC?

Minco Wind I, LLC is in Grady County, Oklahoma, at about 35.280°, -97.976°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Grady County goes 9.4 hours a year without power, the 17th most of 75 counties in Oklahoma. The county's page has the full outage record.

Who operates Minco Wind I, LLC?

It is operated by FPLE Wind, LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Minco Wind I, LLC open?

Its oldest generator still running came online in 2010.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.