Wind power plant · Riverside, CA

Mountain View I & II

Mountain View I & II is a 71 MW wind power plant in Riverside County, California, operated by AES Distributed Energy. Its oldest generator still running came online in 2022. In 2025 it generated 275 GWh, about what 46,000 average California homes use in a year.

Capacity71 MWNameplate, September 2026
Generated275 GWhIn 2025
Capacity factor44%Share of the most it could make, 2025
Generators1Oldest from 2022

Mountain View I & II in context

Among the 112 wind plants in California in the EIA's inventory, it is the 38th largest, about 1.1% of the state's 6.6 GW of wind capacity.

Riverside County has 121 power plants of 1 MW or more with 11 GW in all; Mountain View I & II is 1% of that and the largest of 22 wind plants there.

Its capacity factor of 44% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 275
01002003004002019202120232025275

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Mountain View I & II (outlined) and other plants in Riverside County, shaded. 33.921, -116.564.

Plant facts

Operator
AES Distributed Energy
Sector
IPP Non-CHP
Grid operator
CISO
County
Riverside County, CA
EIA plant ID
55719
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
MVWR Onshore Wind Turbine 71 MW 2022 –

Retired

GeneratorTechnologyCapacityOnlineRetired
GEN2Onshore Wind Turbine22 MW20012021
GENIOnshore Wind Turbine43 MW20012021

Questions

Mountain View I & II, answered

How much power does Mountain View I & II produce?

Mountain View I & II has 71 MW of capacity from one generator. In 2025 it generated 275 GWh, 44% of the most it could have made running flat out all year (its capacity factor).

How many homes does Mountain View I & II power?

Its 2025 output of 275 GWh equals the yearly electricity use of about 46,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Mountain View I & II?

Mountain View I & II is in Riverside County, California, at about 33.921°, -116.564°. It is one of 121 power plants of 1 MW or more in the county. The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.

Who operates Mountain View I & II?

It is operated by AES Distributed Energy (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did Mountain View I & II open?

Its oldest generator still running came online in 2022.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.