Storage power plant · Riverside, CA
Ortega Grid, LLC
Ortega Grid, LLC is a 20 MW storage power plant in Riverside County, California, operated by Ortega Grid, LLC. Its oldest generator still running came online in 2025.
Ortega Grid, LLC in context
Among the 156 storage plants in California in the EIA's inventory, it is the 90th largest, about 0.1% of the state's 13 GW of storage capacity.
Riverside County has 121 power plants of 1 MW or more with 11 GW in all; Ortega Grid, LLC is 0% of that and the 10th largest of 14 storage plants there.
The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.
Where it is
Ortega Grid, LLC (outlined) and other plants in Riverside County, shaded. 33.684, -117.328.
Plant facts
- Operator
- Ortega Grid, LLC
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Riverside County, CA
- EIA plant ID
- 65656
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| HEORG | Batteries | 20 MW · 40 MWh | 2025 | – |
Questions
Ortega Grid, LLC, answered
How much can Ortega Grid, LLC store and deliver?
Ortega Grid, LLC can deliver up to 20 MW and hold 40 MWh of energy, from one battery or storage system. Its net energy in 2025 was -1.8 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Ortega Grid, LLC?
Ortega Grid, LLC is in Riverside County, California, at about 33.684°, -117.328°. It is one of 121 power plants of 1 MW or more in the county. The average electricity customer in Riverside County goes 5.0 hours a year without power, the 37th most of 56 counties in California. The county's page has the full outage record.
Who operates Ortega Grid, LLC?
It is operated by Ortega Grid, LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Ortega Grid, LLC open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.