Solar power plant · Pecos, TX
Pearl Solar
Pearl Solar is a 50 MW solar power plant in Pecos County, Texas, operated by BHE Renewables, LLC. Its oldest generator still running came online in 2017. In 2025 it generated 97 GWh, about what 7,300 average Texas homes use in a year.
Pearl Solar in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 160th largest, about 0.1% of the state's 37 GW of solar capacity.
Pecos County has 31 power plants of 1 MW or more with 3.7 GW in all; Pearl Solar is 1% of that and the 12th largest of 13 solar plants there.
Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Pecos County goes 8.6 hours a year without power, the 132nd most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Pearl Solar (outlined) and other plants in Pecos County, shaded. 30.988, -102.268.
Plant facts
- Operator
- BHE Renewables, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Pecos County, TX
- EIA plant ID
- 60682
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PEARL | Solar Photovoltaic | 50 MW | 2017 | – |
Questions
Pearl Solar, answered
How much power does Pearl Solar produce?
Pearl Solar has 50 MW of capacity from one generator. In 2025 it generated 97 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Pearl Solar power?
Its 2025 output of 97 GWh equals the yearly electricity use of about 7,300 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Pearl Solar?
Pearl Solar is in Pecos County, Texas, at about 30.988°, -102.268°. It is one of 31 power plants of 1 MW or more in the county. The average electricity customer in Pecos County goes 8.6 hours a year without power, the 132nd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Pearl Solar?
It is operated by BHE Renewables, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Pearl Solar open?
Its oldest generator still running came online in 2017.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.