Storage power plant · Bernalillo, NM

Quail Ranch Solar and BESS

Quail Ranch Solar and BESS is a 200 MW storage power plant in Bernalillo County, New Mexico, operated by Quail Ranch Solar and Battery Energy Storage System. Its oldest generator still running came online in 2025. In 2025 it generated 32 GWh, about what 4,100 average New Mexico homes use in a year.

Capacity200 MWNameplate, September 2026
Net energy32 GWhIn 2025
Capacity factor–Not a full year of data
Generators2Oldest from 2025

Quail Ranch Solar and BESS in context

Among the 8 storage plants in New Mexico in the EIA's inventory, it is the 2nd largest, about 23% of the state's 865 MW of storage capacity.

Bernalillo County has 19 power plants of 1 MW or more with 1.2 GW in all; Quail Ranch Solar and BESS is 16% of that and the 2nd largest of 4 storage plants there.

The average electricity customer in Bernalillo County goes 1.8 hours a year without power, the 16th most of 20 counties in New Mexico. The county's page has the full outage record.

Where it is

Quail Ranch Solar and BESS (outlined) and other plants in Bernalillo County, shaded. 35.199, -106.857.

Plant facts

Operator
Quail Ranch Solar and Battery Energy Storage System
Sector
IPP Non-CHP
Grid operator
PNM
County
Bernalillo County, NM
EIA plant ID
67204
  • Solar100 MW50%
  • Storage100 MW50%
Where New Mexico's power comes from → New Mexico power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
QRPV Solar Photovoltaic 100 MW 2025 –
QRBES Batteries 100 MW · 400 MWh 2026 –

Questions

Quail Ranch Solar and BESS, answered

How much can Quail Ranch Solar and BESS store and deliver?

Quail Ranch Solar and BESS can deliver up to 200 MW and hold 400 MWh of energy, from 2 storage units. Its net energy in 2025 was 32 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.

Where is Quail Ranch Solar and BESS?

Quail Ranch Solar and BESS is in Bernalillo County, New Mexico, at about 35.199°, -106.857°. It is one of 19 power plants of 1 MW or more in the county. The average electricity customer in Bernalillo County goes 1.8 hours a year without power, the 16th most of 20 counties in New Mexico. The county's page has the full outage record.

Who operates Quail Ranch Solar and BESS?

It is operated by Quail Ranch Solar and Battery Energy Storage System (EIA sector: IPP Non-CHP), and it feeds balancing authority PNM.

When did Quail Ranch Solar and BESS open?

Its oldest generator still running came online in 2025.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average New Mexico home's 638 kWh a month in 2025. Methodology.