Solar power plant · Fresno, CA

San Joaquin Solar

San Joaquin Solar is a 21 MW solar power plant in Fresno County, California, operated by GASNA 6P, LLC. Its oldest generator still running came online in 2018. In 2025 it generated 22 GWh, about what 3,800 average California homes use in a year.

Capacity21 MWNameplate, September 2026
Generated22 GWhIn 2025
Capacity factor12%Share of the most it could make, 2025
Generators2Oldest from 2018

San Joaquin Solar in context

Among the 967 solar plants in California in the EIA's inventory, it is the 161st largest, about 0.1% of the state's 32 GW of solar capacity.

Fresno County has 105 power plants of 1 MW or more with 5.9 GW in all; San Joaquin Solar is 0% of that and the 12th largest of 73 solar plants there.

Its capacity factor of 12% in 2025 is lower than the 20% typical for solar plants across the US.

The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0102030405020182019202020212022202320242025GWh 22
01020304050201920212023202522

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

San Joaquin Solar (outlined) and other plants in Fresno County, shaded. 36.527, -120.148.

Plant facts

Operator
GASNA 6P, LLC
Sector
IPP Non-CHP
Grid operator
CISO
County
Fresno County, CA
EIA plant ID
60678
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SJ1A Solar Photovoltaic 20 MW 2018 –
SJ1B Solar Photovoltaic 1.5 MW 2019 –

Questions

San Joaquin Solar, answered

How much power does San Joaquin Solar produce?

San Joaquin Solar has 21 MW of capacity from 2 generators. In 2025 it generated 22 GWh, 12% of the most it could have made running flat out all year (its capacity factor).

How many homes does San Joaquin Solar power?

Its 2025 output of 22 GWh equals the yearly electricity use of about 3,800 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is San Joaquin Solar?

San Joaquin Solar is in Fresno County, California, at about 36.527°, -120.148°. It is one of 105 power plants of 1 MW or more in the county. The average electricity customer in Fresno County goes 3.5 hours a year without power, the 48th most of 56 counties in California. The county's page has the full outage record.

Who operates San Joaquin Solar?

It is operated by GASNA 6P, LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did San Joaquin Solar open?

Its oldest generator still running came online in 2018.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.