Solar power plant · Kern, CA

Solar Star 1

Solar Star 1 is a 318 MW solar power plant in Kern County, California, operated by Solar Star California XIX, LLC. Its oldest generator still running came online in 2014. In 2025 it generated 897 GWh, about what 151,000 average California homes use in a year.

Capacity318 MWNameplate, September 2026
Generated897 GWhIn 2025
Capacity factor32%Share of the most it could make, 2025
Generators7Oldest from 2014

Solar Star 1 in context

Among the 967 solar plants in California in the EIA's inventory, it is the 19th largest, about 1.0% of the state's 32 GW of solar capacity.

Kern County has 268 power plants of 1 MW or more with 19 GW in all; Solar Star 1 is 2% of that and the 5th largest of 158 solar plants there.

Its capacity factor of 32% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Kern County goes 4.3 hours a year without power, the 43rd most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,0001,20020182019202020212022202320242025GWh 897
02004006008001,0001,2002019202120232025897

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Solar Star 1 (outlined) and other plants in Kern County, shaded. 34.818, -118.404.

Plant facts

Operator
Solar Star California XIX, LLC
Sector
IPP Non-CHP
Grid operator
CISO
County
Kern County, CA
EIA plant ID
58388
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SS16 Solar Photovoltaic 65 MW 2014 –
SS13 Solar Photovoltaic 59 MW 2014 –
SS11 Solar Photovoltaic 54 MW 2015 –
SS12 Solar Photovoltaic 54 MW 2015 –
AVS1 Solar Photovoltaic 39 MW 2014 –
SS14 Solar Photovoltaic 33 MW 2015 –
SS15 Solar Photovoltaic 15 MW 2014 –

Questions

Solar Star 1, answered

How much power does Solar Star 1 produce?

Solar Star 1 has 318 MW of capacity from 7 generators. In 2025 it generated 897 GWh, 32% of the most it could have made running flat out all year (its capacity factor).

How many homes does Solar Star 1 power?

Its 2025 output of 897 GWh equals the yearly electricity use of about 151,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Solar Star 1?

Solar Star 1 is in Kern County, California, at about 34.818°, -118.404°. It is one of 268 power plants of 1 MW or more in the county. The average electricity customer in Kern County goes 4.3 hours a year without power, the 43rd most of 56 counties in California. The county's page has the full outage record.

Who operates Solar Star 1?

It is operated by Solar Star California XIX, LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did Solar Star 1 open?

Its oldest generator still running came online in 2014.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.