Wind power plant · Kenedy, TX
Stella Wind Farm
Stella Wind Farm is a 201 MW wind power plant in Kenedy County, Texas, operated by RWE Americas, LLC. Its oldest generator still running came online in 2018. In 2025 it generated 589 GWh, about what 44,000 average Texas homes use in a year.
Stella Wind Farm in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 91st largest, about 0.4% of the state's 45 GW of wind capacity.
Kenedy County has 5 power plants of 1 MW or more with 1.1 GW in all; Stella Wind Farm is 18% of that and the 5th largest of 5 wind plants there.
Its capacity factor of 33% in 2025 is close to the 32% typical for wind plants across the US.
The average electricity customer in Kenedy County goes 46 hours a year without power. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Stella Wind Farm (outlined) and other plants in Kenedy County, shaded. 26.942, -97.642.
Plant facts
- Operator
- RWE Americas, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Kenedy County, TX
- EIA plant ID
- 59063
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| WT1 | Onshore Wind Turbine | 201 MW | 2018 | – |
Nearby
Other plants in Kenedy County
Questions
Stella Wind Farm, answered
How much power does Stella Wind Farm produce?
Stella Wind Farm has 201 MW of capacity from one generator. In 2025 it generated 589 GWh, 33% of the most it could have made running flat out all year (its capacity factor).
How many homes does Stella Wind Farm power?
Its 2025 output of 589 GWh equals the yearly electricity use of about 44,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Stella Wind Farm?
Stella Wind Farm is in Kenedy County, Texas, at about 26.942°, -97.642°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Kenedy County goes 46 hours a year without power. The county's page has the full outage record.
Who operates Stella Wind Farm?
It is operated by RWE Americas, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Stella Wind Farm open?
Its oldest generator still running came online in 2018.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.