Solar power plant · Tulare, CA
Tropico Solar PV Plant
Tropico Solar PV Plant is a 14 MW solar power plant in Tulare County, California, operated by Arevon Energy, Inc.. Its oldest generator still running came online in 2016. In 2025 it generated 32 GWh, about what 5,500 average California homes use in a year.
Tropico Solar PV Plant in context
Among the 967 solar plants in California in the EIA's inventory, it is the 273rd largest, about 0.0% of the state's 32 GW of solar capacity.
Tulare County has 66 power plants of 1 MW or more with 1.4 GW in all; Tropico Solar PV Plant is 1% of that and the 14th largest of 49 solar plants there.
Its capacity factor of 26% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Tulare County goes 4.2 hours a year without power, the 44th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Tropico Solar PV Plant (outlined) and other plants in Tulare County, shaded. 35.832, -119.056.
Plant facts
- Operator
- Arevon Energy, Inc.
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Tulare County, CA
- EIA plant ID
- 59599
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Solar Photovoltaic | 14 MW | 2016 | – |
Questions
Tropico Solar PV Plant, answered
How much power does Tropico Solar PV Plant produce?
Tropico Solar PV Plant has 14 MW of capacity from one generator. In 2025 it generated 32 GWh, 26% of the most it could have made running flat out all year (its capacity factor).
How many homes does Tropico Solar PV Plant power?
Its 2025 output of 32 GWh equals the yearly electricity use of about 5,500 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Tropico Solar PV Plant?
Tropico Solar PV Plant is in Tulare County, California, at about 35.832°, -119.056°. It is one of 66 power plants of 1 MW or more in the county. The average electricity customer in Tulare County goes 4.2 hours a year without power, the 44th most of 56 counties in California. The county's page has the full outage record.
Who operates Tropico Solar PV Plant?
It is operated by Arevon Energy, Inc. (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Tropico Solar PV Plant open?
Its oldest generator still running came online in 2016.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.