Solar power plant · San Bernardino, CA
Aratina Solar Center 1A
Aratina Solar Center 1A is a 195 MW solar power plant in San Bernardino County, California, operated by 64NB 8me LLC. Its oldest generator still running came online in 2026.
Aratina Solar Center 1A in context
Among the 967 solar plants in California in the EIA's inventory, it is the 58th largest, about 0.6% of the state's 32 GW of solar capacity.
San Bernardino County has 129 power plants of 1 MW or more with 7.1 GW in all; Aratina Solar Center 1A is 3% of that and the 6th largest of 91 solar plants there.
The average electricity customer in San Bernardino County goes 6.8 hours a year without power, the 33rd most of 56 counties in California. The county's page has the full outage record.
Where it is
Aratina Solar Center 1A (outlined) and other plants in San Bernardino County, shaded. 34.988, -117.572.
Plant facts
- Operator
- 64NB 8me LLC
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- San Bernardino County, CA
- EIA plant ID
- 68661
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 64NB8 | Solar Photovoltaic | 120 MW | 2026 | – |
| 64BES | Batteries | 75 MW · 300 MWh | 2026 | – |
Questions
Aratina Solar Center 1A, answered
How much power does Aratina Solar Center 1A produce?
Aratina Solar Center 1A has 195 MW of capacity from 2 generators. No full year of generation is reported yet.
Where is Aratina Solar Center 1A?
Aratina Solar Center 1A is in San Bernardino County, California, at about 34.988°, -117.572°. It is one of 129 power plants of 1 MW or more in the county. The average electricity customer in San Bernardino County goes 6.8 hours a year without power, the 33rd most of 56 counties in California. The county's page has the full outage record.
Who operates Aratina Solar Center 1A?
It is operated by 64NB 8me LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Aratina Solar Center 1A open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.