Solar power plant · Madera, CA

Borden Solar Farm

Borden Solar Farm is a 50 MW solar power plant in Madera County, California, operated by 41MB 8me, LLC. Its oldest generator still running came online in 2020. In 2025 it generated 113 GWh, about what 19,000 average California homes use in a year.

Capacity50 MWNameplate, September 2026
Generated113 GWhIn 2025
Capacity factor26%Share of the most it could make, 2025
Generators1Oldest from 2020

Borden Solar Farm in context

Among the 967 solar plants in California in the EIA's inventory, it is the 134th largest, about 0.2% of the state's 32 GW of solar capacity.

Madera County has 24 power plants of 1 MW or more with 496 MW in all; Borden Solar Farm is 10% of that and the largest of 15 solar plants there.

Its capacity factor of 26% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Madera County goes 11 hours a year without power, the 25th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

050100150202020212022202320242025GWh 113
050100150202020212022202320242025113

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Borden Solar Farm (outlined) and other plants in Madera County, shaded. 36.941, -119.960.

Plant facts

Operator
41MB 8me, LLC
Sector
IPP Non-CHP
Grid operator
CISO
County
Madera County, CA
EIA plant ID
59531
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
BRDN Solar Photovoltaic 50 MW 2020 –

Questions

Borden Solar Farm, answered

How much power does Borden Solar Farm produce?

Borden Solar Farm has 50 MW of capacity from one generator. In 2025 it generated 113 GWh, 26% of the most it could have made running flat out all year (its capacity factor).

How many homes does Borden Solar Farm power?

Its 2025 output of 113 GWh equals the yearly electricity use of about 19,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Borden Solar Farm?

Borden Solar Farm is in Madera County, California, at about 36.941°, -119.960°. It is one of 24 power plants of 1 MW or more in the county. The average electricity customer in Madera County goes 11 hours a year without power, the 25th most of 56 counties in California. The county's page has the full outage record.

Who operates Borden Solar Farm?

It is operated by 41MB 8me, LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did Borden Solar Farm open?

Its oldest generator still running came online in 2020.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.