Wind power plant · Scurry, TX
Canyon Wind Project, LLC
Canyon Wind Project, LLC is a 309 MW wind power plant in Scurry County, Texas, operated by Canyon Wind Project, LLC. Its oldest generator still running came online in 2024. In 2025 it generated 1.1 TWh, about what 82,000 average Texas homes use in a year.
Canyon Wind Project, LLC in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 19th largest, about 0.7% of the state's 45 GW of wind capacity.
Scurry County has 14 power plants of 1 MW or more with 2.6 GW in all; Canyon Wind Project, LLC is 12% of that and the largest of 7 wind plants there.
Its capacity factor of 40% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Scurry County goes 2.5 hours a year without power, the 228th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Canyon Wind Project, LLC (outlined) and other plants in Scurry County, shaded. 32.631, -101.008.
Plant facts
- Operator
- Canyon Wind Project, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Scurry County, TX
- EIA plant ID
- 60271
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| WT1 | Onshore Wind Turbine | 309 MW | 2024 | – |
Questions
Canyon Wind Project, LLC, answered
How much power does Canyon Wind Project, LLC produce?
Canyon Wind Project, LLC has 309 MW of capacity from one generator. In 2025 it generated 1.1 TWh, 40% of the most it could have made running flat out all year (its capacity factor).
How many homes does Canyon Wind Project, LLC power?
Its 2025 output of 1.1 TWh equals the yearly electricity use of about 82,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Canyon Wind Project, LLC?
Canyon Wind Project, LLC is in Scurry County, Texas, at about 32.631°, -101.008°. It is one of 14 power plants of 1 MW or more in the county. The average electricity customer in Scurry County goes 2.5 hours a year without power, the 228th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Canyon Wind Project, LLC?
It is operated by Canyon Wind Project, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Canyon Wind Project, LLC open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.