Wind power plant · Scurry, TX
Coyote Wind LLC
Coyote Wind LLC is a 243 MW wind power plant in Scurry County, Texas, operated by EDF Renewable Asset Holdings, Inc.. Its oldest generator still running came online in 2021. In 2025 it generated 646 GWh, about what 49,000 average Texas homes use in a year.
Coyote Wind LLC in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 56th largest, about 0.5% of the state's 45 GW of wind capacity.
Scurry County has 14 power plants of 1 MW or more with 2.6 GW in all; Coyote Wind LLC is 9% of that and the 3rd largest of 7 wind plants there.
Its capacity factor of 30% in 2025 is close to the 32% typical for wind plants across the US.
The average electricity customer in Scurry County goes 2.5 hours a year without power, the 228th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Coyote Wind LLC (outlined) and other plants in Scurry County, shaded. 32.849, -100.867.
Plant facts
- Operator
- EDF Renewable Asset Holdings, Inc.
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Scurry County, TX
- EIA plant ID
- 63655
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| COY | Onshore Wind Turbine | 243 MW | 2021 | – |
Questions
Coyote Wind LLC, answered
How much power does Coyote Wind LLC produce?
Coyote Wind LLC has 243 MW of capacity from one generator. In 2025 it generated 646 GWh, 30% of the most it could have made running flat out all year (its capacity factor).
How many homes does Coyote Wind LLC power?
Its 2025 output of 646 GWh equals the yearly electricity use of about 49,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Coyote Wind LLC?
Coyote Wind LLC is in Scurry County, Texas, at about 32.849°, -100.867°. It is one of 14 power plants of 1 MW or more in the county. The average electricity customer in Scurry County goes 2.5 hours a year without power, the 228th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Coyote Wind LLC?
It is operated by EDF Renewable Asset Holdings, Inc. (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Coyote Wind LLC open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.