Solar power plant · Scurry, TX
Lumina Solar Project
Lumina Solar Project is a 487 MW solar power plant in Scurry County, Texas, operated by IPX Power USA, LLC. Its oldest generator still running came online in 2024. In 2025 it generated 680 GWh, about what 51,000 average Texas homes use in a year.
Lumina Solar Project in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 9th largest, about 1.3% of the state's 37 GW of solar capacity.
Scurry County has 14 power plants of 1 MW or more with 2.6 GW in all; Lumina Solar Project is 18% of that and the 2nd largest of 2 solar plants there.
The average electricity customer in Scurry County goes 2.5 hours a year without power, the 228th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Lumina Solar Project (outlined) and other plants in Scurry County, shaded. 32.901, -100.983.
Plant facts
- Operator
- IPX Power USA, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Scurry County, TX
- EIA plant ID
- 65645
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| LUMIN | Solar Photovoltaic | 327 MW | 2024 | – |
| LU1BA | Batteries | 160 MW · 320 MWh | 2025 | – |
Questions
Lumina Solar Project, answered
How much power does Lumina Solar Project produce?
Lumina Solar Project has 487 MW of capacity from 2 generators. In 2025 it generated 680 GWh.
How many homes does Lumina Solar Project power?
Its 2025 output of 680 GWh equals the yearly electricity use of about 51,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Lumina Solar Project?
Lumina Solar Project is in Scurry County, Texas, at about 32.901°, -100.983°. It is one of 14 power plants of 1 MW or more in the county. The average electricity customer in Scurry County goes 2.5 hours a year without power, the 228th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Lumina Solar Project?
It is operated by IPX Power USA, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Lumina Solar Project open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.