Wind power plant · Converse, WY
Cedar Springs I
Cedar Springs I is a 200 MW wind power plant in Converse County, Wyoming, operated by Cedar Springs Wind, LLC. Its oldest generator still running came online in 2020. In 2025 it generated 700 GWh, about what 70,000 average Wyoming homes use in a year.
Cedar Springs I in context
Among the 28 wind plants in Wyoming in the EIA's inventory, it is the 8th largest, about 4.2% of the state's 4.7 GW of wind capacity.
Converse County has 10 power plants of 1 MW or more with 2.4 GW in all; Cedar Springs I is 8% of that and the 3rd largest of 9 wind plants there.
Its capacity factor of 40% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Converse County goes 7.5 hours a year without power, the 2nd most of 20 counties in Wyoming. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Cedar Springs I (outlined) and other plants in Converse County, shaded. 43.020, -105.472.
Plant facts
- Operator
- Cedar Springs Wind, LLC
- Sector
- IPP Non-CHP
- Grid operator
- PACE
- County
- Converse County, WY
- EIA plant ID
- 63914
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 82633 | Onshore Wind Turbine | 200 MW | 2020 | – |
Questions
Cedar Springs I, answered
How much power does Cedar Springs I produce?
Cedar Springs I has 200 MW of capacity from one generator. In 2025 it generated 700 GWh, 40% of the most it could have made running flat out all year (its capacity factor).
How many homes does Cedar Springs I power?
Its 2025 output of 700 GWh equals the yearly electricity use of about 70,000 average Wyoming homes (835 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Cedar Springs I?
Cedar Springs I is in Converse County, Wyoming, at about 43.020°, -105.472°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Converse County goes 7.5 hours a year without power, the 2nd most of 20 counties in Wyoming. The county's page has the full outage record.
Who operates Cedar Springs I?
It is operated by Cedar Springs Wind, LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.
When did Cedar Springs I open?
Its oldest generator still running came online in 2020.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Wyoming home's 835 kWh a month in 2025. Methodology.