Solar power plant · San Bernardino, CA
Lockhart Solar PV IV, LLC
Lockhart Solar PV IV, LLC is a 80 MW solar power plant in San Bernardino County, California, operated by Terra-Gen Operating Co-Solar. Its oldest generator still running came online in 2026.
Lockhart Solar PV IV, LLC in context
Among the 967 solar plants in California in the EIA's inventory, it is the 113th largest, about 0.3% of the state's 32 GW of solar capacity.
San Bernardino County has 129 power plants of 1 MW or more with 7.1 GW in all; Lockhart Solar PV IV, LLC is 1% of that and the 17th largest of 91 solar plants there.
The average electricity customer in San Bernardino County goes 6.8 hours a year without power, the 33rd most of 56 counties in California. The county's page has the full outage record.
Where it is
Lockhart Solar PV IV, LLC (outlined) and other plants in San Bernardino County, shaded. 35.032, -117.338.
Plant facts
- Operator
- Terra-Gen Operating Co-Solar
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- San Bernardino County, CA
- EIA plant ID
- 67510
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| LOC4 | Solar Photovoltaic | 80 MW | 2026 | – |
Questions
Lockhart Solar PV IV, LLC, answered
How much power does Lockhart Solar PV IV, LLC produce?
Lockhart Solar PV IV, LLC has 80 MW of capacity from one generator. No full year of generation is reported yet.
Where is Lockhart Solar PV IV, LLC?
Lockhart Solar PV IV, LLC is in San Bernardino County, California, at about 35.032°, -117.338°. It is one of 129 power plants of 1 MW or more in the county. The average electricity customer in San Bernardino County goes 6.8 hours a year without power, the 33rd most of 56 counties in California. The county's page has the full outage record.
Who operates Lockhart Solar PV IV, LLC?
It is operated by Terra-Gen Operating Co-Solar (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Lockhart Solar PV IV, LLC open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.