Hydro power plant · Placer, CA
Middle Fork
Middle Fork is a 122 MW hydro power plant in Placer County, California, operated by Placer County Water Agency - (CA). Its oldest generator still running came online in 1966. In 2025 it generated 424 GWh, about what 71,000 average California homes use in a year.
Middle Fork in context
Among the 238 hydro plants in California in the EIA's inventory, it is the 26th largest, about 1.2% of the state's 10 GW of hydro capacity.
Placer County has 21 power plants of 1 MW or more with 773 MW in all; Middle Fork is 16% of that and the largest of 13 hydro plants there.
Its capacity factor of 40% in 2025 is higher than the 34% typical for hydro plants across the US.
The average electricity customer in Placer County goes 9.6 hours a year without power, the 28th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Middle Fork (outlined) and other plants in Placer County, shaded. 39.025, -120.596.
Plant facts
- Operator
- Placer County Water Agency - (CA)
- Sector
- Electric Utility
- Grid operator
- CISO
- County
- Placer County, CA
- EIA plant ID
- 425
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 61 MW | 1966 | – |
| 2 | Conventional Hydroelectric | 61 MW | 1966 | – |
Questions
Middle Fork, answered
How much power does Middle Fork produce?
Middle Fork has 122 MW of capacity from 2 generators. In 2025 it generated 424 GWh, 40% of the most it could have made running flat out all year (its capacity factor).
How many homes does Middle Fork power?
Its 2025 output of 424 GWh equals the yearly electricity use of about 71,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Middle Fork?
Middle Fork is in Placer County, California, at about 39.025°, -120.596°. It is one of 21 power plants of 1 MW or more in the county. The average electricity customer in Placer County goes 9.6 hours a year without power, the 28th most of 56 counties in California. The county's page has the full outage record.
Who operates Middle Fork?
It is operated by Placer County Water Agency - (CA) (EIA sector: Electric Utility), and it feeds the California ISO.
When did Middle Fork open?
Its oldest generator still running came online in 1966.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.