Biomass power plant · Placer, CA
Rio Bravo Rocklin
Rio Bravo Rocklin is a 28 MW biomass power plant in Placer County, California, operated by Rio Bravo Rocklin. Its oldest generator still running came online in 1989. In 2025 it generated 147 GWh, about what 25,000 average California homes use in a year.
Rio Bravo Rocklin in context
Among the 157 other-fuel plants in California in the EIA's inventory, it is the 48th largest, about 0.6% of the state's 4.9 GW of other-fuel capacity.
Placer County has 21 power plants of 1 MW or more with 773 MW in all; Rio Bravo Rocklin is 4% of that and the largest of 4 biomass plants there.
Its capacity factor of 60% in 2025 is higher than the 25% typical for biomass plants across the US.
The average electricity customer in Placer County goes 9.6 hours a year without power, the 28th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Rio Bravo Rocklin (outlined) and other plants in Placer County, shaded. 38.832, -121.314.
Plant facts
- Operator
- Rio Bravo Rocklin
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Placer County, CA
- EIA plant ID
- 10772
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Wood/Wood Waste Biomass | 28 MW | 1989 | – |
Questions
Rio Bravo Rocklin, answered
How much power does Rio Bravo Rocklin produce?
Rio Bravo Rocklin has 28 MW of capacity from one generator. In 2025 it generated 147 GWh, 60% of the most it could have made running flat out all year (its capacity factor).
How many homes does Rio Bravo Rocklin power?
Its 2025 output of 147 GWh equals the yearly electricity use of about 25,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Rio Bravo Rocklin?
Rio Bravo Rocklin is in Placer County, California, at about 38.832°, -121.314°. It is one of 21 power plants of 1 MW or more in the county. The average electricity customer in Placer County goes 9.6 hours a year without power, the 28th most of 56 counties in California. The county's page has the full outage record.
Who operates Rio Bravo Rocklin?
It is operated by Rio Bravo Rocklin (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Rio Bravo Rocklin open?
Its oldest generator still running came online in 1989.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.