Hydro power plant · Placer, CA
Ralston
Ralston is a 79 MW hydro power plant in Placer County, California, operated by Placer County Water Agency - (CA). Its oldest generator still running came online in 1966. In 2025 it generated 303 GWh, about what 51,000 average California homes use in a year.
Ralston in context
Among the 238 hydro plants in California in the EIA's inventory, it is the 43rd largest, about 0.8% of the state's 10 GW of hydro capacity.
Placer County has 21 power plants of 1 MW or more with 773 MW in all; Ralston is 10% of that and the 2nd largest of 13 hydro plants there.
Its capacity factor of 44% in 2025 is higher than the 34% typical for hydro plants across the US.
The average electricity customer in Placer County goes 9.6 hours a year without power, the 28th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Ralston (outlined) and other plants in Placer County, shaded. 39.001, -120.725.
Plant facts
- Operator
- Placer County Water Agency - (CA)
- Sector
- Electric Utility
- Grid operator
- CISO
- County
- Placer County, CA
- EIA plant ID
- 427
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 79 MW | 1966 | – |
Questions
Ralston, answered
How much power does Ralston produce?
Ralston has 79 MW of capacity from one generator. In 2025 it generated 303 GWh, 44% of the most it could have made running flat out all year (its capacity factor).
How many homes does Ralston power?
Its 2025 output of 303 GWh equals the yearly electricity use of about 51,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Ralston?
Ralston is in Placer County, California, at about 39.001°, -120.725°. It is one of 21 power plants of 1 MW or more in the county. The average electricity customer in Placer County goes 9.6 hours a year without power, the 28th most of 56 counties in California. The county's page has the full outage record.
Who operates Ralston?
It is operated by Placer County Water Agency - (CA) (EIA sector: Electric Utility), and it feeds the California ISO.
When did Ralston open?
Its oldest generator still running came online in 1966.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.