Wind power plant · Howard, TX
Panther Creek Wind Farm I
Panther Creek Wind Farm I is a 143 MW wind power plant in Howard County, Texas, operated by RWE Americas, LLC. Its oldest generator still running came online in 2008. In 2025 it generated 530 GWh, about what 40,000 average Texas homes use in a year.
Panther Creek Wind Farm I in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 165th largest, about 0.3% of the state's 45 GW of wind capacity.
Howard County has 7 power plants of 1 MW or more with 657 MW in all; Panther Creek Wind Farm I is 22% of that and the largest of 5 wind plants there.
Its capacity factor of 42% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Howard County goes 6.5 hours a year without power, the 178th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Panther Creek Wind Farm I (outlined) and other plants in Howard County, shaded. 32.101, -101.451.
Plant facts
- Operator
- RWE Americas, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Howard County, TX
- EIA plant ID
- 56920
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 143 MW | 2008 | – |
Questions
Panther Creek Wind Farm I, answered
How much power does Panther Creek Wind Farm I produce?
Panther Creek Wind Farm I has 143 MW of capacity from one generator. In 2025 it generated 530 GWh, 42% of the most it could have made running flat out all year (its capacity factor).
How many homes does Panther Creek Wind Farm I power?
Its 2025 output of 530 GWh equals the yearly electricity use of about 40,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Panther Creek Wind Farm I?
Panther Creek Wind Farm I is in Howard County, Texas, at about 32.101°, -101.451°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Howard County goes 6.5 hours a year without power, the 178th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Panther Creek Wind Farm I?
It is operated by RWE Americas, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Panther Creek Wind Farm I open?
Its oldest generator still running came online in 2008.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.