Solar power plant · Millard, UT

Pavant Solar III

Pavant Solar III is a 20 MW solar power plant in Millard County, Utah, operated by Invenergy Services LLC. Its oldest generator still running came online in 2016. In 2025 it generated 44 GWh, about what 4,800 average Utah homes use in a year.

Capacity20 MWNameplate, September 2026
Generated44 GWhIn 2025
Capacity factor25%Share of the most it could make, 2025
Generators1Oldest from 2016

Pavant Solar III in context

Among the 56 solar plants in Utah in the EIA's inventory, it is the 31st largest, about 0.7% of the state's 3.0 GW of solar capacity.

Millard County has 4 power plants of 1 MW or more with 1.2 GW in all; Pavant Solar III is 2% of that and the 3rd largest of 3 solar plants there.

Its capacity factor of 25% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Millard County goes 4.1 hours a year without power, the 8th most of 23 counties in Utah. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020406020182019202020212022202320242025GWh 44
0204060201920212023202544

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Pavant Solar III (outlined) and other plants in Millard County, shaded. 39.154, -112.360.

Plant facts

Operator
Invenergy Services LLC
Sector
IPP Non-CHP
Grid operator
PACE
County
Millard County, UT
EIA plant ID
60886
Where Utah's power comes from → Utah power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
PSIII Solar Photovoltaic 20 MW 2016 –

Questions

Pavant Solar III, answered

How much power does Pavant Solar III produce?

Pavant Solar III has 20 MW of capacity from one generator. In 2025 it generated 44 GWh, 25% of the most it could have made running flat out all year (its capacity factor).

How many homes does Pavant Solar III power?

Its 2025 output of 44 GWh equals the yearly electricity use of about 4,800 average Utah homes (761 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Pavant Solar III?

Pavant Solar III is in Millard County, Utah, at about 39.154°, -112.360°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Millard County goes 4.1 hours a year without power, the 8th most of 23 counties in Utah. The county's page has the full outage record.

Who operates Pavant Solar III?

It is operated by Invenergy Services LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.

When did Pavant Solar III open?

Its oldest generator still running came online in 2016.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Utah home's 761 kWh a month in 2025. Methodology.