Solar power plant · Merced, CA
Quinto Solar PV Project
Quinto Solar PV Project is a 108 MW solar power plant in Merced County, California, operated by Arevon Energy, Inc.. Its oldest generator still running came online in 2015. In 2025 it generated 243 GWh, about what 41,000 average California homes use in a year.
Quinto Solar PV Project in context
Among the 967 solar plants in California in the EIA's inventory, it is the 94th largest, about 0.3% of the state's 32 GW of solar capacity.
Merced County has 29 power plants of 1 MW or more with 1.0 GW in all; Quinto Solar PV Project is 10% of that and the 2nd largest of 18 solar plants there.
Its capacity factor of 26% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Merced County goes 2.3 hours a year without power, the 54th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Quinto Solar PV Project (outlined) and other plants in Merced County, shaded. 37.130, -121.052.
Plant facts
- Operator
- Arevon Energy, Inc.
- Sector
- IPP Non-CHP
- Grid operator
- CISO
- County
- Merced County, CA
- EIA plant ID
- 59339
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| SSC13 | Solar Photovoltaic | 108 MW | 2015 | – |
Questions
Quinto Solar PV Project, answered
How much power does Quinto Solar PV Project produce?
Quinto Solar PV Project has 108 MW of capacity from one generator. In 2025 it generated 243 GWh, 26% of the most it could have made running flat out all year (its capacity factor).
How many homes does Quinto Solar PV Project power?
Its 2025 output of 243 GWh equals the yearly electricity use of about 41,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Quinto Solar PV Project?
Quinto Solar PV Project is in Merced County, California, at about 37.130°, -121.052°. It is one of 29 power plants of 1 MW or more in the county. The average electricity customer in Merced County goes 2.3 hours a year without power, the 54th most of 56 counties in California. The county's page has the full outage record.
Who operates Quinto Solar PV Project?
It is operated by Arevon Energy, Inc. (EIA sector: IPP Non-CHP), and it feeds the California ISO.
When did Quinto Solar PV Project open?
Its oldest generator still running came online in 2015.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.