Wind power plant · Morrow, OR

Wheatridge Hybrid

Wheatridge Hybrid is a 280 MW wind power plant in Morrow County, Oregon, operated by Wheatridge Wind Holdings, LLC. Its oldest generator still running came online in 2020. In 2025 it generated 668 GWh, about what 64,000 average Oregon homes use in a year.

Capacity280 MWNameplate, September 2026
Generated668 GWhIn 2025
Capacity factor27%Share of the most it could make, 2025
Generators3Oldest from 2020

Wheatridge Hybrid in context

Among the 50 wind plants in Oregon in the EIA's inventory, it is the 5th largest, about 6.6% of the state's 4.3 GW of wind capacity.

Morrow County has 19 power plants of 1 MW or more with 1.9 GW in all; Wheatridge Hybrid is 14% of that and the largest of 14 wind plants there.

Its capacity factor of 27% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Morrow County goes 2.4 hours a year without power, the 30th most of 32 counties in Oregon. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,000202020212022202320242025GWh 668
02004006008001,000202020212022202320242025668

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Wheatridge Hybrid (outlined) and other plants in Morrow County, shaded. 45.560, -119.634.

Plant facts

Operator
Wheatridge Wind Holdings, LLC
Sector
IPP Non-CHP
Grid operator
BPAT
County
Morrow County, OR
EIA plant ID
62745
  • Wind200 MW71%
  • Solar50 MW18%
  • Storage30 MW11%
Where Oregon's power comes from → Oregon power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
WIND Onshore Wind Turbine 200 MW 2020 –
SOLAR Solar Photovoltaic 50 MW 2022 –
BTRY Batteries 30 MW · 120 MWh 2022 –

Questions

Wheatridge Hybrid, answered

How much power does Wheatridge Hybrid produce?

Wheatridge Hybrid has 280 MW of capacity from 3 generators. In 2025 it generated 668 GWh, 27% of the most it could have made running flat out all year (its capacity factor).

How many homes does Wheatridge Hybrid power?

Its 2025 output of 668 GWh equals the yearly electricity use of about 64,000 average Oregon homes (866 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Wheatridge Hybrid?

Wheatridge Hybrid is in Morrow County, Oregon, at about 45.560°, -119.634°. It is one of 19 power plants of 1 MW or more in the county. The average electricity customer in Morrow County goes 2.4 hours a year without power, the 30th most of 32 counties in Oregon. The county's page has the full outage record.

Who operates Wheatridge Hybrid?

It is operated by Wheatridge Wind Holdings, LLC (EIA sector: IPP Non-CHP), and it feeds the Bonneville Power Administration.

When did Wheatridge Hybrid open?

Its oldest generator still running came online in 2020.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Oregon home's 866 kWh a month in 2025. Methodology.