Natural gas power plant · Fort Bend, TX
Braes Bayou Plant
Braes Bayou Plant is a 484 MW natural gas power plant in Fort Bend County, Texas, operated by ProEnergy Services. Its oldest generator still running came online in 2022. In 2025 it generated 190 GWh, about what 14,000 average Texas homes use in a year.
Braes Bayou Plant in context
Among the 309 natural gas plants in Texas in the EIA's inventory, it is the 74th largest, about 0.6% of the state's 83 GW of natural gas capacity.
Fort Bend County has 25 power plants of 1 MW or more with 7.4 GW in all; Braes Bayou Plant is 7% of that and the 2nd largest of 11 natural gas plants there.
Its capacity factor of 5% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Fort Bend County goes 5.5 hours a year without power, the 190th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Braes Bayou Plant (outlined) and other plants in Fort Bend County, shaded. 29.480, -95.620.
Plant facts
- Operator
- ProEnergy Services
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Fort Bend County, TX
- EIA plant ID
- 64383
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CTG-1 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
| CTG-2 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
| CTG-3 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
| CTG-4 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
| CTG-5 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
| CTG-6 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
| CTG-7 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
| CTG-8 | Natural Gas Fired Combustion Turbine | 61 MW | 2022 | – |
Questions
Braes Bayou Plant, answered
How much power does Braes Bayou Plant produce?
Braes Bayou Plant has 484 MW of capacity from 8 generators. In 2025 it generated 190 GWh, 5% of the most it could have made running flat out all year (its capacity factor).
How many homes does Braes Bayou Plant power?
Its 2025 output of 190 GWh equals the yearly electricity use of about 14,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Braes Bayou Plant?
Braes Bayou Plant is in Fort Bend County, Texas, at about 29.480°, -95.620°. It is one of 25 power plants of 1 MW or more in the county. The average electricity customer in Fort Bend County goes 5.5 hours a year without power, the 190th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Braes Bayou Plant?
It is operated by ProEnergy Services (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Braes Bayou Plant open?
Its oldest generator still running came online in 2022.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.