Solar power plant · Fort Bend, TX
Old 300 Solar Center, LLC
Old 300 Solar Center, LLC is a 430 MW solar power plant in Fort Bend County, Texas, operated by Old 300 Solar Center, LLC. Its oldest generator still running came online in 2024. In 2025 it generated 902 GWh, about what 68,000 average Texas homes use in a year.
Old 300 Solar Center, LLC in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 16th largest, about 1.2% of the state's 37 GW of solar capacity.
Fort Bend County has 25 power plants of 1 MW or more with 7.4 GW in all; Old 300 Solar Center, LLC is 6% of that and the largest of 6 solar plants there.
Its capacity factor of 24% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Fort Bend County goes 5.5 hours a year without power, the 190th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Old 300 Solar Center, LLC (outlined) and other plants in Fort Bend County, shaded. 29.334, -95.825.
Plant facts
- Operator
- Old 300 Solar Center, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Fort Bend County, TX
- EIA plant ID
- 64133
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 2222 | Solar Photovoltaic | 430 MW | 2024 | – |
Questions
Old 300 Solar Center, LLC, answered
How much power does Old 300 Solar Center, LLC produce?
Old 300 Solar Center, LLC has 430 MW of capacity from one generator. In 2025 it generated 902 GWh, 24% of the most it could have made running flat out all year (its capacity factor).
How many homes does Old 300 Solar Center, LLC power?
Its 2025 output of 902 GWh equals the yearly electricity use of about 68,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Old 300 Solar Center, LLC?
Old 300 Solar Center, LLC is in Fort Bend County, Texas, at about 29.334°, -95.825°. It is one of 25 power plants of 1 MW or more in the county. The average electricity customer in Fort Bend County goes 5.5 hours a year without power, the 190th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Old 300 Solar Center, LLC?
It is operated by Old 300 Solar Center, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Old 300 Solar Center, LLC open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.