Solar power plant · Fort Bend, TX

Fort Bend Solar LLC

Fort Bend Solar LLC is a 240 MW solar power plant in Fort Bend County, Texas, operated by Acciona Energy USA Global, LLC. Its oldest generator still running came online in 2023. In 2025 it generated 527 GWh, about what 40,000 average Texas homes use in a year.

Capacity240 MWNameplate, September 2026
Generated527 GWhIn 2025
Capacity factor25%Share of the most it could make, 2025
Generators1Oldest from 2023

Fort Bend Solar LLC in context

Among the 250 solar plants in Texas in the EIA's inventory, it is the 59th largest, about 0.6% of the state's 37 GW of solar capacity.

Fort Bend County has 25 power plants of 1 MW or more with 7.4 GW in all; Fort Bend Solar LLC is 3% of that and the 2nd largest of 6 solar plants there.

Its capacity factor of 25% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Fort Bend County goes 5.5 hours a year without power, the 190th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0200400600202320242025GWh 527
0200400600202320242025527

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Fort Bend Solar LLC (outlined) and other plants in Fort Bend County, shaded. 29.560, -95.980.

Plant facts

Operator
Acciona Energy USA Global, LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Fort Bend County, TX
EIA plant ID
63985
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
FBS Solar Photovoltaic 240 MW 2023 –

Questions

Fort Bend Solar LLC, answered

How much power does Fort Bend Solar LLC produce?

Fort Bend Solar LLC has 240 MW of capacity from one generator. In 2025 it generated 527 GWh, 25% of the most it could have made running flat out all year (its capacity factor).

How many homes does Fort Bend Solar LLC power?

Its 2025 output of 527 GWh equals the yearly electricity use of about 40,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Fort Bend Solar LLC?

Fort Bend Solar LLC is in Fort Bend County, Texas, at about 29.560°, -95.980°. It is one of 25 power plants of 1 MW or more in the county. The average electricity customer in Fort Bend County goes 5.5 hours a year without power, the 190th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Fort Bend Solar LLC?

It is operated by Acciona Energy USA Global, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Fort Bend Solar LLC open?

Its oldest generator still running came online in 2023.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.